Bids final step to raise Tamiami Trail, flow water to Everglades

Contractors have until the beginning of next month to bid on a project to raise a 6.5-mile segment of the Tamiami Trail, the final step in infrastructure to increase the flow of fresh water to the Everglades and Florida Bay.

“The deadline for bids is early July,” said Alecia Collins, deputy communications director for the Florida Department of Transportation, which is co-managing the project with the National Parks Service. Tamiami Trail, the southernmost 275 miles of US 41, runs through Everglades National Park.

The Florida Department of Transportation advertised the Tamiani Trail Next Steps Phase 2 Project on April 28 as a low-bid design-build contract. Ms. Collins said the department won’t release information related to responses prior to the final selection at the end of July, but typically bids from contractors come in just before deadline.

“Construction is expected to begin this fall,” she said, “and will be completed in spring 2024.”

Gov. Ron DeSantis recently called the project “a key component of the Comprehensive Everglades Restoration Plan,” which was authorized by Congress in 2000 to “restore, preserve, and protect” the South Florida ecosystem while providing for other water-related needs of the region.

The plan, estimated to cost more than $10.5 billion within a 35-year timeline, is the largest hydrologic restoration project ever undertaken in the US, according to the National Park Service’s website.

Improvements to the Tamiami Trail began in 2008 with construction by the Army Corps of Engineers of a one-mile bridge at the trail’s eastern end. In 2019 the Florida Department of Transportation completed Tamiami Trail Next Steps Phase 1, which involved removing the existing roadbed and constructing two new bridges.

Gov. DeSantis announced a year ago that, with $60 million from the US Department of Transportation and $40 million from the state, full funding for Phase 2 of the Tamiami Trail Next Steps project had been secured. Ms. Collins confirmed that the budget remains unchanged.

The Comprehensive Everglades Restoration Plan seeks to repair injuries done to the Everglades ecosystem during construction of the Tamiami Trail in the 1920s. The roadway has blocked water flow from Lake Okeechobee to Florida Bay ever since.

“Because we have such a flat landscape, the way to make water flow in South Florida is to raise the water level,” said Steve Davis, communications director & senior ecologist at the Everglades Foundation, a nonprofit dedicated to restoration of the Everglades and nearby protected natural areas.

“Bridges help,” he said, “but the real key is to raise the water level to get more water under the bridges. Because the trail was not built to modern roadway standards, we currently can’t do that.”

The Tamiami Trail Next Steps Phase 2 project, Dr. Davis said, “will scrape it down to bedrock at an elevation that allows us to raise it to levels that have been cut off for nearly a century.”

The next piece, he said, will be construction of the Everglades Reservoir, described in the restoration plan as “an above-ground reservoir directly south of Lake Okeechobee, in the 500,000 acres of sugarcane fields that make up the Everglades Agricultural Area.”

“We hope,” Dr. Davis said, “to see funding from the federal government to start this year.”

Let's block ads! (Why?)



"flow" - Google News
June 10, 2020 at 11:57AM
https://ift.tt/2BOXPff

Bids final step to raise Tamiami Trail, flow water to Everglades - Miami Today
"flow" - Google News
https://ift.tt/2Sw6Z5O
https://ift.tt/2zNW3tO

Bagikan Berita Ini

Related Posts :

0 Response to "Bids final step to raise Tamiami Trail, flow water to Everglades - Miami Today"

Post a Comment


Powered by Blogger.